Everything about Henry L Gantt totally explained
Henry Laurence Gantt, A.B., M.E. (1861-
23 November 1919) was a
mechanical engineer and
management consultant who is most famous for developing the
Gantt chart in the
1910s. These Gantt charts were employed on major infrastructure projects including the
Hoover Dam and
Interstate highway system and continue to be an important tool in
project management.
Biography
Gantt was born in
Calvert County, Maryland, USA. He graduated from
McDonogh School in 1878 and then went on to
Johns Hopkins University. He then worked as a teacher and draughtsman before becoming a mechanical engineer. In 1887, he joined
Frederick W. Taylor in applying scientific management principles to their work at
Midvale Steel and
Bethlehem Steel—working there with Taylor until 1893. In his later career as a management consultant—following the invention of the Gantt chart—he also designed the 'task and bonus' system of wage payment and additional measurement methods
worker efficiency and productivity. Henry Gantt is listed under Stevens Institute of Technology alumni and roommate to Frederick Winslow Taylor (M.E., 1883).
Gantt charts
The following discussion of Gantt charts originally appeared in Herrmann (2005):
It is important to note that Gantt created many different types of charts. Moreover, Gantt designed his charts so that foremen or other
supervisors could quickly know whether production was on schedule, ahead of schedule, or behind schedule. Modern project management software includes this critical function even now.
Gantt (1903) describes two types of
balances: the “man’s record,” which shows what each worker should do and did do, and the
daily balance of work, which shows the amount of work to be done and the amount that's done. Gantt gives an example with orders that will require many days to complete. The daily balance has rows for each day and columns for each part or each operation. At the top of each column is the amount needed. The amount entered in the appropriate cell is the number of parts done each day and the cumulative total for that part. Heavy horizontal lines indicate the starting date and the date that the order should be done. According to Gantt, the graphical daily balance is “a method of scheduling and recording work.” In this article, Gantt also describes the use of
production cards for assigning work to each operator and recording how much was done each day.
In
Work, Wages, and Profits (originally published in 1916), Gantt explicitly discusses
scheduling, especially in the job shop environment. He proposes giving to the foreman each day an “order of work” that's an ordered list of jobs to be done that day. Moreover, he discusses the need to coordinate activities to avoid “interferences.” However, he also warns that the most elegant schedules created by planning offices are useless if they're ignored, a situation that he observed.
In
Organizing for Work (originally published in 1919), Gantt gives two principles for his charts: one, measure activities by the amount of
time needed to complete them; two, the space on the chart can be used the represent the
amount of the activity that should have been done in that time. Gantt shows a progress chart that indicates for each month of the year, using a thin horizontal line, the number of items produced during that month. In addition, a thick horizontal line indicates the number of items produced during the year. Each row in the chart corresponds to an order for parts from a specific contractor, and each row indicates the starting month and ending month of the deliveries. It is the closest thing to the Gantt charts typically used today in scheduling systems, though it's at a higher level than machine scheduling.
Gantt’s machine record chart and man record chart are quite similar, though they show both the actual working time for each day and the cumulative working time for a week. Each row of the chart corresponds to an individual machine or operator. These charts don't indicate which tasks were to be done, however.
A novel method of displaying interdependencies of processes to increase visibility of production schedules was invented (and aplicated) in 1896 by
Karol Adamiecki and described in "Przeglad Techniczny" No 17, 18, 19 and 20 of 1909. In 1931, Adamiecki published a number of articles popularizing this diagram, which he called the Harmonogram or Harmonograf. With minor modifications, this chart is now more commonly referred to as the Gantt Chart.
Contributions
Henry Gantt's legacy to production management is the following:
- The Gantt chart: Still accepted as an important management tool today, it provides a graphic schedule for the planning and controlling of work, and recording progress towards stages of a project. The chart has a modern variation, Program Evaluation and Review Technique (PERT).
- Industrial Efficiency: Industrial efficiency can only be produced by the application of scientific analysis to all aspects of the work in progress. The industrial management role is to improve the system by eliminating chance and accidents.
- The Task And Bonus System: He linked the bonus paid to managers to how well they taught their employees to improve performance.
- The social responsibility of business: He believed that businesses have obligations to the welfare of society that they operate in.
The
American Society of Mechanical Engineers (ASME) awards an annual medal in honor of Henry Laurence Gantt.
Further Information
Get more info on 'Henry L Gantt'.
|
External Link Exchanges
Do you know how hard it is to get a link from a large encyclopaedia? Well we're different and will prove it. To get a link from us just add the following HTML to your site on a relevant page:
<a href="http://henry_gantt.totallyexplained.com">Henry Gantt Totally Explained</a>
Then simply click through this link from your web page. Our crawlers will verify your link, extract the title of your web page and instantly add a link back to it. If you like you can remove the words Totally Explained and embed the link in article text.
As long as your link remains in place, we'll keep our link to you right here. Please play fair - our crawlers are watching. Your site must be closely related to this one's topic. Any kind of spamming, dubious practises or removing the link will result in your link from us being dropped and, potentially, your whole site being banned. |